# Question 65: The Purchase Order, the Acknowledgment, and the Cap

## Your role

You represent AlloyWorks, a seller of industrial control boards, after Meridian Fabrication claims production losses from defective boards. Determine the contract terms formed through the purchase order, acknowledgment, and later emails, calculate recoverable damages, and identify the operative liability cap.

## Governing law

Assume the following Commercial Code rules apply:

1. A purchase order inviting shipment is an offer. A timely definite expression of acceptance forms a contract even though it contains additional or different terms, unless the acceptance is expressly conditional on the offeror's assent to the new terms.

2. An acceptance is expressly conditional only when it clearly communicates that the accepting party is unwilling to proceed unless the offeror assents. A statement that seller terms “apply” or “govern” is not enough by itself.

3. Between merchants, an additional term does not become part of the contract if the offer expressly limits acceptance to its terms, the added term materially alters the bargain, or the offeror timely objects.

4. Conflicting different terms in exchanged forms are both displaced unless the parties later expressly agree to one. Code gap rules govern the displaced subject.

5. A contract may be modified without new consideration by clear mutual assent. An email exchange between authorized commercial representatives may modify terms even when earlier forms conflict.

6. A term sent only on an invoice after formation does not become part of the contract without assent.

7. Direct damages include reasonable cover, repair, and inspection costs caused by breach. Consequential damages include production interruption and other secondary loss and are recoverable only if foreseeable at contracting, proved with reasonable certainty, and not avoidable through reasonable mitigation.

8. A damages cap and consequential-damages exclusion are distinct. Agreement to a cap does not imply agreement to exclude a category of damages.

9. Damages are reduced by proven mitigation savings. A cap is applied after determining otherwise recoverable damages.

10. Lost profits from a particular downstream customer are not foreseeable unless the seller had reason to know of that customer or comparable special exposure at contracting.

## Documents and facts

On February 1, Meridian sent AlloyWorks a purchase order for 1,200 control boards at $1,250 each, total price $1,500,000, for delivery April 1. The purchase order states:

* “Acceptance is expressly limited to these terms.”
* AlloyWorks warrants conformity to specification.
* AlloyWorks is liable for direct damages and foreseeable production-interruption loss.
* “Aggregate supplier liability shall not exceed 200 percent of the total purchase-order price.”

On February 2, AlloyWorks sent an acknowledgment stating, “We accept Purchase Order 4817. Seller's standard terms apply.” Its terms provide:

* Delivery April 15.
* Liability capped at the price paid for affected units.
* No consequential damages.

The acknowledgment does not state that AlloyWorks will refuse to perform unless Meridian assents to those terms.

On February 3, AlloyWorks' sales director emailed Meridian's procurement director:

> “We cannot accept uncapped exposure. We can accept your 200 percent overall cap if downtime damages remain subject to that cap and delivery moves to April 15.”

Meridian's procurement director replied:

> “Agreed: April 15 and all recoverable damages remain under the purchase order's 200 percent cap. We do not agree to the affected-unit cap or a blanket exclusion of downtime damages.”

The sales director responded, “Booked.” Both directors had authority to modify the order.

AlloyWorks delivered on April 15. Three hundred boards were defective. Meridian proves:

* $620,000 in cover and repair cost.
* $80,000 in reasonable inspection cost.
* $2,600,000 in production-interruption loss. AlloyWorks knew at contracting that the boards controlled Meridian's only active line.
* $140,000 in expedited freight caused by the interruption.
* $1,100,000 in lost profit from a particular customer renewal. Meridian never identified that customer or renewal to AlloyWorks before contracting.
* $240,000 in production savings from transferring some work to an affiliate. The savings reduce the interruption loss.

An invoice sent after delivery repeated AlloyWorks' affected-unit cap and consequential-damages exclusion. Meridian never signed or discussed the invoice terms.

Meridian demands $4,300,000 after subtracting mitigation but including all listed categories. AlloyWorks argues that liability is capped at $375,000, the price of the 300 affected boards, and that all consequential damages are excluded.

## Assignment

Analyze:

* Contract formation through the purchase order and acknowledgment.
* Whether the acknowledgment was expressly conditional.
* Treatment of the conflicting caps and consequential-damages terms in the forms.
* The effect of the February 3 email exchange.
* The post-delivery invoice.
* Recoverability and arithmetic for each damages category.
* Mitigation and the order in which the cap applies.
* The exact uncapped recoverable amount and capped amount.
* AlloyWorks' concrete settlement and litigation position.

---

---